Puhoi to Warkworth Motorway

Project Progress
100%

Client: NX2 – Fletcher / Acciona Joint Venture
Location: Warkworth

Ross Reid was engaged by the main Contractor Fletcher ACCIONA to undertake the early enabling works in this $700M project. Following from the initial scope of felling trees through a native bush, Ross Reid was further tasked with the establishment of access tracks, environmental controls, early earthworks, geotechnical investigations and ground stabilisation works. We were tasked with breaking some of the first ground in this mountainous terrain. Our well thought out construction strategy and our expert executions enabled us to maintain a safe working environment. It created a workable area for heavy machineries from what was previously inaccessible terrain.

Project Scope

Clearing and grubbing, earthworks, construction and surfacing of access tracks, construction of environmental controls, ground stabilisation works.